How to Apply for a Building Licence in Port Moresby
1. Download the Required Forms
-
Building Application Form: Obtain the official application form. Click here
-
Building Application Checklists: Depending on your project type (e.g., major, minor, fencing, interior fit-out), download the relevant checklist. Click here
2. Prepare Supporting Documents
Ensure you have the following documents ready:
-
Land Ownership Documents: Land title or lease agreement.
-
Architectural and Engineering Plans: At least two complete sets, stamped and signed by:
-
NCD Physical Planning Board
-
NCD Fire Authority
-
Eda Ranu (water and sewerage)
-
NCDC Health Authority
-
NCDC Development Engineer
-
PNG Power (for electrical approvals)
-
-
Detailed Site Plan: Scale of 1:500, showing site services and connection points.
-
Floor Plans, Elevations, and Sections: Properly dimensioned to scales not less than 1:100.
-
Construction Details: Scaled not less than 1:20.
-
Structural Certification: Certificate of structural adequacy, stamped and signed.
-
Mechanical, Electrical, and Hydraulic Drawings: If applicable, stamped and signed by certified engineers.
-
Material Specifications: Description of materials to be used.
-
Occupancy Statement: Nature of occupancy for each portion of the building.
-
Estimated Construction Cost: Total estimated cost of the project.
-
Professional Details: Names and contact information of the architect, structural engineer, services engineer, and builder
3. Calculate and Pay Applicable Fees
-
Fee Calculation: Fees are based on the estimated cost of construction. Use the fee calculation form provided by NCDC. Click here
-
Payment: Pay the calculated fees at the NCDC cashier and obtain official receipts.
4. Submit Your Application
-
In-Person Submission: Visit the NCDC Regulatory Services Department at Waigani Drive, opposite Vision City.
-
Submission Days: Applications are accepted on Mondays, Tuesdays, and Wednesdays.
-
Online Submission: Alternatively, you can apply online through the NCDC Online Services portal
5. Application Review Process
-
Assessment: The Building Authority will review your application for compliance with the Building Act Chapter 301
-
Additional Information: You may be requested to provide further details or make necessary corrections.
-
Approval: Upon satisfactory review, the Building Board will grant approval.
6. Permit Issuance
Building Permit: Once approved, you will receive your building permit, allowing you to commence construction.
Contact
325 0601 / 325 1541